Escalator Installation – Heathrow T5

Escalators 9 & 10 Serving apron level to departures level

Project overview

To install 6 Schindler escalators into the Terminal 5 TTS Link tunnel, all units split into 3 sections, top, middle and bottom. All delivered Air side via a window at apron level and lowered down onto the TTS platform during daytime hours. The sections were taking across the TTS live train track in night time hours onto the centre platform and lowered down once again to the minus 4 level TTS level link tunnel.

The escalators were then transported from terminal C to terminal A, and then to Terminal B via the TTS link tunnel using the 25E Valla Crane and skates.

The sections were joined in each well and lifted into position and then fully built with all balustrades and profiles before commissioning and testing.

The first 6 escalators were delivered, joined, installed and fully built including commissioning and testing within a 2 week period with day and night shift work to meet this very tight timescale.

Escalators 7, 8, 9 and 10 were installed at a later date towards the end of the project were we had to work extra shifts and weekends to meet the deadline handover date.

During the installation of escalators 7, 8, 9 & 10, the site engineers won the MACE safety award for September 2014 and were awarded vouchers to spend in local stores.

Liftout Project Manager, John Bostock was also awarded the Safe Contractor award in November 2014 for all the work carried out during the installation period for this project.

Download the PDF fact sheet on this project here

“Thanks for all yours and Liftout’s efforts throughout the project, you and your teams professionalism and willingness to get the job done is greatly appreciated”
Mark Lowes, Mechanical Project Manager, Mace Group

“At the awards event my nomination for you was read out. It talked about you and your team and your safe, proactive approach. Thanks for all your efforts throughout the project; I look forward to working with Lift-Out in the future.”
Sean O’Grady MCIOB, Project Manager, Mace Aviation